PERT: Planning When Durations Are Uncertain

How long will drilling take? PERT asks for three answers, not one.

Lesson notes

Key points

Definitions

PERT estimates
Optimistic a, most likely m, pessimistic b: best, typical and worst-case durations for one activity.

Takeaway: PERT: tₑ = (a + 4m + b) ÷ 6, then sum along the critical path.

Quick check: PERT expected time with a=2, m=5, b=8?
  1. 5 days
  2. 4 days
  3. 6 days

(2 + 20 + 8) ÷ 6 = 30 ÷ 6 = 5 days.

Three estimatesExpected timeWorked exampleProject probability